Bu Dop 3 is the biggest project among Bu Dop series which is on over 4.7 ha in Thanh Hoa, Bu Dop ward, Binh Phuoc Province.
It was challenging to Palma Group as commencement date is on Nov 2020. The solar plant is using top qualified materials such as: AE solar panel, Inverter SMA core II -110Kwp, Helukabel cable …. There was up to 150 workers on the peak schedule. The solar plant joined the nation grid on 30th Dec 2020 right on the deadline of FIT2.
Total capacity: 6 MWp